NYCT Steinway Tube Rehabilitation

This project included installation of approximately twenty-six electrical isolation flanges into existing 8” sump discharge lines within the Steinway tube.

 

In addition the isolation flanges, the entire 8” pipe system was isolated from its hangers using electrical insulative tape (approximately 1500 locations). This work was all completed during 53 hr track outages.

 

Value: $2,900,000

Contractor: Rising Sun Construction